MedMart Construction Update: 06162011


CONSTRUCTION UPDATE - 6/16/11

PROJECT UPDATES :: JUNE 16, 2011

Laura Johnston/The Plain Dealer
NORTH OF LAKESIDE AVENUE, THE NORTH BRIDGE DEMOLITION CONTINUED ON MALL C AND IS NOW 95% COMPLETE. DEBRIS REMOVAL WILL CONTINUE. INTERIOR DEMOLITION IS 85% COMPLETE IN EXISTING EXHIBIT HALLS ‘’C’’ AND ‘’D’’ ON THE LOWER LEVEL. UNDERNEATH LAKESIDE AVENUE, TEMPORARY STEEL SUPPORT OF THE ROADWAY CONTINUES WITH TARGETED COLUMN DEMOLITION SCHEDULED FOR NEXT WEEK. MALL C DEMOLITION CONTINUED WITH ADDITIONAL ROOF REMOVAL CONTINUING THIS WEEK. MICRO-PILE WORK CONTINUES IN THE BALLROOM AREA.

ON MALL B, PRE-CORES CAISSONS WORK IS NEARING COMPLETION WITH 63 OF THE 66 COMPLETED. MEANWHILE, FOUR CAISSONS HAVE BEEN COMPLETED ALONG WITH 111 MICRO-PILES COMPLETED ALONG ST. CLAIR AVENUE.

FOUNDATION WORK CONTINUES ON THE FUTURE CONVENTION CENTER CONCOURSE LEVEL AND STAIR WALLS ARE BEING FORMED FOR CONCRETE.

ON THE MEDICAL MART SITE, BACKFILLING IS 90% COMPLETE AND WORK HAS COMMENCED IN THE AREA WHERE THE FORMER CONVENTION CENTER RAMP OFF ONTARIO AVENUE WAS LOCATED. MASS EXCAVATION WORK IS 70% COMPLETED ON THE MEDICAL MART SITE. SOLDIER PILE INSTALLATION IS COMPLETE IN THIS AREA.

PUBLIC AUDITORIUM SEPARATION WORK CONTINUES WITH HVAC DEMOLITION WORK 95% COMPLETED.