MedMart Construction Update: 05122011

From clevelandmedicalmartonline.com:



Construction Update - 5/12/11

PROJECT UPDATES :: 
The demolition and haul out of materials and debris from the five buildings on the future Medical Mart site has been completed. The 113 Building was demolished in April, the last structure to be demolished at the corner of St. Clair and Ontario. In three months, crews demolished the Justice Center parking deck, the Chicago Title and County Annex buildings, the Sportsmans Restaurant, and the 113 Building. Soldier pile installation has been completed around the former 113 Building while backfilling, lagging and tie-backs continue. 
Demolition is also proceeding on schedule on the Convention Center and Malls B and C. On the north side of Lakeside Avenue, Mall C roof demolition is 95% complete. Interior demolition in existing Exhibit Halls C and D on the lower level of Mall C is roughly 95% complete. Demolition of the loading dock connection at Lakeside Avenue and the East Stair Tower began earlier in the week.
The balance of remaining demolition work on Mall B is located on the southeast corner of the project. Continued demolition of the topping slab and 4’ interstitial sand volume is approximately 85% complete. The highly-visible metal sheeting project along St. Clair Avenue continues moving to the west.
Read more here:

0 comments: