Recreation Center
o Punch list underway.
o FF&E delivery and install underway.
o Final inspections complete.
o Occupancy attained.
o Building opens August 28th.
Fenn Towero Furniture delivery and assembly in progress.
o Design of retail space moving forward.
o Building opens August 15th.
Parker Hannafin Administration Center / Hall
o Cast stone delivered and to be installed.
o Interior framing inside Parker Hannifin Hall underway.
o Brick façade work on the exterior of Administration Center continuing.
East Parking Garage
o Glass installation underway.
o West façade brick install underway.
o Electrical installation progressing.
o Elevator installation slated to be complete end of July/beginning of August.
o Bridge from Garage to Recreation Center to be installed the week of August 12th.
Main Classroom Stair Tower Phase 1Ao Foundation installation has begun.
Main Classroom Plaza Build Out Phase 1B
o Bid documents have been received and are being reviewed.
Student Center Phase II
o Schematic Design kicked off August 2nd.