Tuesday, August 08, 2006

August Project Status Report for Cleveland State University

Cleveland State University Project Status Report

Recreation Center
o Punch list underway.
o FF&E delivery and install underway.
o Final inspections complete.
o Occupancy attained.
o Building opens August 28th.

Fenn Tower
o Furniture delivery and assembly in progress.
o Design of retail space moving forward.
o Building opens August 15th.

Parker Hannafin Administration Center / Hall
o Cast stone delivered and to be installed.
o Interior framing inside Parker Hannifin Hall underway.
o Brick façade work on the exterior of Administration Center continuing.

East Parking Garage
o Glass installation underway.
o West façade brick install underway.
o Electrical installation progressing.
o Elevator installation slated to be complete end of July/beginning of August.
o Bridge from Garage to Recreation Center to be installed the week of August 12th.

Main Classroom Stair Tower Phase 1A
o Foundation installation has begun.

Main Classroom Plaza Build Out Phase 1B
o Bid documents have been received and are being reviewed.

Student Center Phase II
o Schematic Design kicked off August 2nd.