Monday, July 10, 2006

CSU Project Staus for July

With the summer construction season well under way, there is busy work all over campus - not to metion on Euclid Avenue. Here are the status of current state funded projects.

Recreation Center
o Interior finishes are near completion.
o Mechanical, electrical, plumbing, and technology systems are being installed.
o Site work is underway.
o Final FF&E purchases are being completed.

Parker Hannafin Administration Center / Hall
o Roof on Administration Center is complete.
o Floors in the Administration Building are complete.
o Metal studs, ductwork, sprinkler lines and electrical rough-in are complete in the 2nd & 3rd floor
Administration Building.
o Administration Building exterior masonry has begun.

East Parking Garage
o Elevated decks are complete.
o Structural steel for stairs and elevators are complete.
o Brick and Masonry has begun.
o Glass and roof for stairs to start July 10th.
o Elevators to start July 24th.

Fenn Tower Residence Hall
o Punch list underway, suites on floors 9-17 complete.
o Cleaning of tower suites underway.
o Furniture delivery scheduled for July 5th.
o Window installation complete.
o Drywall installation, paint, flooring (carpet, vinyl tile, & painted concrete), cabinetry and plumbing fixtures
for floors Basement – 8th is 60% complete.

Main Classroom Stair Tower Phase 1A
o Demolition of quad lecture halls complete.
o Mechanical and electrical tie-ins are underway.
o Excavation for stair tower foundation to begin early July.

Main Classroom Plaza Build Out Phase 1B
o Design Development drawings are at 95% and are being reviewed.

Student Center Phase II
o Contracts have been approved.

0 comments: